The paper present the concept of stability assessing the of solutions which are construction schedules. Rank have been obtained through the use of task scheduling rules and the application of the KASS software. The aim of the work is the choice of the equivalent solution in terms of the total time of the project. The selected solution optimization task should be characterized by the highest resistance to harmful environmental risk factors. To asses the stability of schedule simulation technique was used.
The basic element of a project organizing construction works is a schedule. The preparation of the data necessary to specify the timings of the construction completion as indicated in the schedule involves information that is uncertain and hard to quantify. The article presents the methods of building a schedule which includes a fuzzy amount of labour, time standards and number of workers. The proposed procedure allows determining the real deadline for project completion, taking into account variable factors affecting the duration of the individual works.